Quantity Takeoff Methods: Long Wall, Short Wall & Centre Line

Learn how to calculate quantities for foundation, brickwork, and concrete using long wall–short wall and centre line methods. Worked examples for single-room buildings.

5 min read
By Yojo Team
வெளியிடப்பட்டது: 10 மார்ச், 2026
Quantity Takeoff Methods: Long Wall, Short Wall & Centre Line - Yojo construction management blog

Introduction

Quantity takeoff means measuring volumes and areas from drawings to arrive at material quantities. For buildings, earthwork, foundation concrete, brickwork in plinth and superstructure can be worked out by two main methods:

  1. Long wall – short wall method
  2. Centre line method
  3. Partly centre line and partly long wall–short wall

This guide explains each method with a worked example for a single-room load-bearing structure.

Long Wall – Short Wall Method

Definitions

  • Long wall – Wall along the length of the room
  • Short wall – Wall perpendicular to the long wall

How to Get Lengths

  1. Find centre line lengths of each wall.
  2. Long wall (out to out) = Centre line length + (½ × breadth) at each end
  3. Short wall (in to in) = Centre line length − (½ × breadth) at each end

As you move from earthwork → foundation → footings → basement → superstructure:

  • Long wall length decreases (breadth reduces)
  • Short wall length increases

Quantity = Length × Breadth × Height (or depth).

Example: Single Room 5.3 m × 4.3 m (internal)

Assume:

  • Foundation width: 0.9 m, depth: 1.4 m (0.3 + 0.5 + 0.6)
  • CC bed: 0.9 m × 0.3 m
  • RR masonry footings: 0.6 m × 0.5 m
  • RR masonry basement: 0.45 m × 0.6 m
  • Brickwork superstructure: 0.30 m × 3.0 m

Centre line length = 2 × (5.3 + 4.3) = 19.2 m

Earthwork excavation:

  • Long wall L = 5.3 + 0.45 + 0.45 = 6.2 m
  • Short wall L = 4.3 − 0.45 − 0.45 = 3.4 m
  • Q = 2 × 6.2 × 0.9 × 1.4 + 2 × 3.4 × 0.9 × 1.4 = 24.192 cum

CC (1:4:8) bed:

  • Q = 2 × 6.2 × 0.9 × 0.3 + 2 × 3.4 × 0.9 × 0.3 = 5.184 cum

RR masonry footings:

  • Long wall L = 5.3 + 0.3 + 0.3 = 5.9 m
  • Short wall L = 4.3 − 0.3 − 0.3 = 3.7 m
  • Q = 2 × 5.9 × 0.6 × 0.5 + 2 × 3.7 × 0.6 × 0.5 = 5.76 cum

RR masonry basement:

  • Long wall L = 5.3 + 0.225 + 0.225 = 5.75 m
  • Short wall L = 4.3 − 0.225 − 0.225 = 3.85 m
  • Q = 2 × 5.75 × 0.45 × 0.6 + 2 × 3.85 × 0.45 × 0.6 = 5.184 cum

Brickwork superstructure:

  • Long wall L = 5.3 + 0.15 + 0.15 = 5.6 m
  • Short wall L = 4.3 − 0.15 − 0.15 = 4.0 m
  • Q = 2 × 5.6 × 0.30 × 3.0 + 2 × 4.0 × 0.30 × 3.0 = 17.28 cum (before door/window deductions)

Centre Line Method

When to Use

Suitable when walls have similar cross-section. Total centre line length × breadth × depth gives quantity in one step.

Junction Adjustment

Where cross walls or partitions join the main wall, reduce centre line by half the breadth for each junction.

Total centre line = sum of all walls − (½ × breadth) × number of junctions

Same Example by Centre Line

Centre line length = 2(5.3 + 4.3) = 19.2 m (no internal walls)

Earthwork excavation:

  • Q = 19.2 × 0.9 × 1.4 = 24.192 cum

CC bed:

  • Q = 19.2 × 0.9 × 0.3 = 5.184 cum

RR masonry footings:

  • Q = 19.2 × 0.6 × 0.5 = 5.76 cum

RR masonry basement:

  • Q = 19.2 × 0.45 × 0.6 = 5.184 cum

Brickwork superstructure:

  • Q = 19.2 × 0.30 × 3.0 = 17.28 cum

Same answers as long wall–short wall, with less calculation.

Partly Centre Line and Partly Long Wall–Short Wall

Use when:

  • External walls – Same thickness all around → centre line method
  • Internal walls – Different thickness or levels → long wall–short wall method

This is common in practice for buildings with different foundation levels or wall thicknesses.

Choosing a Method

SituationPreferred method
Simple rectangular room, same sectionCentre line
Multiple rooms, different wall thicknessesLong wall–short wall or partly centre line
Symmetrical layoutCentre line
External + internal with different sectionsPartly centre line

Deductions for Openings

For brickwork in superstructure, deduct door and window openings:

Deduction = Opening length × Wall thickness × Opening height

Deduct lintel volume separately if required. Net brickwork = Gross − Deductions.

Next Steps

உங்கள் கட்டுமான வணிகத்தை மாற்றத் தயாரா?

இன்றே Yojo உடன் உங்கள் தளங்களை திறமையாக நிர்வகிக்கத் தொடங்குங்கள்.

Yojo இலவசமாக முயற்சிக்குங்கள்
Share this article:
மறுஆய்வு செய்தவர்

Construction Management Expert

Senior Construction Consultant at Yojo

10+ Years ExperienceCertified Construction Manager

10+ years அனுபவம்

மறுஆய்வு செய்யப்பட்ட தேதி 10 மார்ச், 2026

Y

Yojo Team பற்றி

10+ ஆண்டுகள் அனுபவத்துடன் கூடிய கட்டுமான மேலாண்மை நிபுணர், இந்திய குத்தகைதாரர்களுக்கு சிறந்த வணிகங்களை உருவாக்க உதவுகிறார். கட்டுமான தளங்களுக்கான டிஜிட்டல் மாற்றத்தில் நிபுணத்துவம்.

கட்டுமான மேலாண்மை நிபுணர்10+ ஆண்டுகள் அனுபவம்
நிபுணத்துவம்:
கட்டுமான மேலாண்மைதொழிலாளர் மேலாண்மைதள செயல்பாடுகள்

Frequently Asked Questions

காத்திருப்புப் பட்டியலில் சேரவும்

நாங்கள் வெளியிடும்போது முதலில் அறியுங்கள்.

காத்திருப்புப் பட்டியலில் சேரவும்

You May Also Like

Detailed Estimates of Buildings: Step-by-Step Guide
Cost & Estimation

Detailed Estimates of Buildings: Step-by-Step Guide

Learn how to prepare detailed estimates—measurement forms, abstract of cost, item-wise rates. Includes single-room and two-room building examples.

மேலும் படிக்கவும்
Units of Measurement in Construction (IS 1200)
Cost & Estimation

Units of Measurement in Construction (IS 1200)

Learn how construction work is measured in India—numbers, running metres, sq m, cum. IS 1200 units for earthwork, concrete, brick, steel, plastering, and more.

மேலும் படிக்கவும்
10×10 அறைக்கு செங்கல், சிமெண்ட் மற்றும் மணல் அளவை எவ்வாறு கணக்கிடுவது
Cost & Estimation

10×10 அறைக்கு செங்கல், சிமெண்ட் மற்றும் மணல் அளவை எவ்வாறு கணக்கிடுவது

இந்தியாவில் 10×10 அறைக்குத் தேவையான செங்கற்கள், சிமெண்ட் மற்றும் மணல்—படிப்படியான கணக்கீடு. சூத்திரங்கள், தீர்க்கப்பட்ட உதாரணம் மற்றும் இலவச செங்கல் கால்குலேட்டர்.

மேலும் படிக்கவும்
Earthwork Calculation: Excavation and Filling
Cost & Estimation

Earthwork Calculation: Excavation and Filling

Learn how to calculate earthwork excavation and filling quantities. Trapezoidal and prismoidal formulae for roads, foundations, and trenches.

மேலும் படிக்கவும்
Approximate Estimates: Plinth Area, Cubical Content & Unit Base Methods
Cost & Estimation

Approximate Estimates: Plinth Area, Cubical Content & Unit Base Methods

Learn three methods for quick project budgets—plinth area, cubical content, and unit base. Worked examples for residential and commercial buildings in India.

மேலும் படிக்கவும்
Introduction to Estimating and Costing in Construction
Cost & Estimation

Introduction to Estimating and Costing in Construction

Learn what estimating and costing means in construction, why it matters for contractors, the types of estimates, and what data you need before starting.

மேலும் படிக்கவும்

முன்கூட்டிய அணுகலைப் பெறுங்கள்

உங்கள் மின்னஞ்சல் மற்றும் WhatsApp எண்ணை உள்ளிடுக. உங்களை முன்கூட்டிய பயனராக சேர்ப்போம் மற்றும் பயன்பாடு இணைப்பை அனுப்புவோம்.

Yojo Team Management
Yojo Sites Management