Introduction

Rate analysis (or data) is the process of working out the cost per unit of each item—e.g., ₹/cum for brickwork, ₹/sq m for plastering.

The rate depends on:

  • Specifications (quality, proportion, method)
  • Material quantities and costs
  • Labour types and wages
  • Site location and conveyance
  • Overheads and profit

This guide explains the process with lead statements and worked examples.

Purpose of Rate Analysis

  1. Unit cost – Actual cost per unit of work
  2. Economy – Identify economical materials and methods
  3. Extra items – Price items not in the contract
  4. Schedule revision – Update rates when material or labour costs change

Lead Statement

Lead = Distance from source of material to construction site (in km).

Conveyance cost depends on lead and road type:

Road typeFactor
Metalled road (MT)1.0
Cart track (CT)1.1
Sandy track (ST)1.4

Equivalent lead = (Lead in MT × 1.0) + (Lead in CT × 1.1) + (Lead in ST × 1.4)

Conveyance charge = Equivalent lead × Rate per km

Example Lead Statement

MaterialRate at sourceLead (km)ConveyanceTotal at site
MTCTST
40 mm HBG metal₹120/cum57
River sand₹15/cum326
Cement₹135/bag24

Material Cost Formulae

Cement (density 1440 kg/cum)

  • 1 bag = 50 kg
  • Cost per cum cement = (Cost per bag / 50) × 1440

Wet vs Dry Concrete

  • 1 cum wet concrete ≈ 1.52 cum dry materials (bulking)
  • Weight of concrete ≈ 1440 kg/cum

Cement in Concrete (e.g., 1:2:4)

Cement (bags) = [1 / (1+2+4)] × 1.52 × Volume × (1440/50)

For 20 cum RCC (1:2:4):

  • Cement = (1/7) × 1.52 × 20 × 28.8 ≈ 125 bags
  • Sand = (2/7) × 1.52 × 20 = 8.69 cum
  • Coarse aggregate = (4/7) × 1.52 × 20 = 17.37 cum

Cement in Mortar (e.g., 1:4)

Cement fills voids in sand. For 1 cum CM (1:4):

  • Cement = (1/4) × 1 = 0.25 cum = 7.2 bags
  • Sand = (4/4) × 1 = 1 cum

Labour Classification

TypeTypical shareUse
Skilled I class30%Mason I, Brick layer I
Skilled II class70%Mason II, Brick layer II
UnskilledMazdoor (men/women)

Rates are taken from standard schedule of rates. For current Indian rates, see our labour rates guide.

Worked Example 1: Plastering CM (1:4), 20 mm Thick, 10 sq m

Data (per 10 sq m):

  • 0.21 cum CM (1:4)
  • 0.66 no. Brick layer I class
  • 1.54 no. Brick layer II class
  • 0.5 no. Men mazdoor
  • 3.2 no. Women mazdoor
  • L.S. sundries

Lead statement: Sand ₹112/cum at site, Cement ₹2,100/tonne at site.

Cost of CM (1:4) for 0.21 cum:

  • Cement = (1/4) × 0.21 × 1.44 × 2100 = ₹158.76
  • Sand = (4/4) × 0.21 × 112 = ₹23.52
  • Total = ₹182.28

Labour (illustrative rates): Mason I ₹100/day, Mason II ₹80/day, Mazdoor ₹60/day, Mixing ₹16/cum.

ItemQtyRateAmount (₹)
CM (1:4)0.21 cum182.28/0.21182.28
Brick layer I0.6610066.00
Brick layer II1.5480123.20
Men mazdoor0.56030.00
Women mazdoor3.260192.00
Mixing0.21 cum163.36
SundriesL.S.3.36
Total₹625 per 10 sq m

Rate = ₹62.50 per sq m.

Worked Example 2: RR Masonry in CM (1:6), 1 cum

Data (per 1 cum):

  • 1.1 cum rough stone
  • 0.34 cum CM (1:6)
  • 0.54 no. Mason I
  • 1.26 no. Mason II
  • 1.4 no. Men mazdoor
  • 1.4 no. Women mazdoor
  • L.S. sundries

Lead statement: Stone ₹350/cum, Sand ₹112/cum, Cement ₹2,100/tonne at site.

Cost of CM (1:6) for 0.34 cum:

  • Cement = (1/6) × 0.34 × 1.44 × 2100 = ₹171.36
  • Sand = (6/6) × 0.34 × 112 = ₹38.08
  • Total = ₹209.44
ItemQtyRateAmount (₹)
Rough stone1.1 cum350385.00
CM (1:6)0.34 cum209.44209.44
Mason I0.5410054.00
Mason II1.2680100.80
Men mazdoor1.46084.00
Women mazdoor1.46084.00
Mixing0.34 cum165.44
SundriesL.S.18.04
Total₹941 per cum

Overheads and Profit

Typical additions:

  • Tools & plant – 1–2% of estimate
  • Overheads – 4% (office, depreciation, staff, etc.)
  • Contractor profit – 8–10% (if not already in rate)

These may be built into the unit rate or added at the end of the abstract.

Next Steps

ਆਪਣੇ ਨਿਰਮਾਣ ਕਾਰੋਬਾਰ ਨੂੰ ਬਦਲਣ ਲਈ ਤਿਆਰ ਹੋ?

ਅੱਜ ਹੀ Yojo ਨਾਲ ਆਪਣੀਆਂ ਸਾਈਟਾਂ ਨੂੰ ਕੁਸ਼ਲਤਾ ਨਾਲ ਪ੍ਰਬੰਧਿਤ ਕਰਨਾ ਸ਼ੁਰੂ ਕਰੋ।

Yojo ਮੁਫਤ ਟਰਾਈ ਕਰੋ
Share this article:
ਸਮੀਖਿਆ ਕੀਤੀ

Construction Management Expert

Senior Construction Consultant at Yojo

10+ Years ExperienceCertified Construction Manager

10+ years ਅਨੁਭੱਵ

ਸਮੀਖਿਆ ਤਾਰੀਖ 10 ਮਾਰਚ 2026

Y

Yojo Team ਬਾਰੇ

10+ ਸਾਲਾਂ ਦੇ ਅਨੁਭੱਵ ਵਾਲਾ ਨਿਰਮਾਣ ਪ੍ਰਬੰਧਨ ਮਾਹਰ, ਭਾਰਤੀ ਠੇਕੇਦਾਰਾਂ ਨੂੰ ਬਿਹਤਰ ਕਾਰੋਬਾਰ ਬਣਾਉਣ ਵਿੱਚ ਮਦਦ ਕਰਦਾ ਹੈ। ਨਿਰਮਾਣ ਸਾਈਟਾਂ ਲਈ ਡਿਜੀਟਲ ਬਦਲਾਅ ਵਿੱਚ ਮਾਹਰਤਾ।

ਨਿਰਮਾਣ ਪ੍ਰਬੰਧਨ ਮਾਹਰ10+ ਸਾਲਾਂ ਦਾ ਅਨੁਭੱਵ
ਮਾਹਰਤਾ:
ਨਿਰਮਾਣ ਪ੍ਰਬੰਧਨਮਜ਼ਦੂਰ ਪ੍ਰਬੰਧਨਸਾਈਟ ਓਪਰੇਸ਼ਨਜ਼

Frequently Asked Questions

ਵੇਟਲਿਸਟ ਵਿੱਚ ਸ਼ਾਮਲ ਹੋਵੋ

ਜਦੋਂ ਅਸੀਂ ਲਾਂਚ ਕਰੀਏ ਤਾਂ ਸਭ ਤੋਂ ਪਹਿਲਾਂ ਜਾਣੋ।

ਵੇਟਲਿਸਟ ਵਿੱਚ ਸ਼ਾਮਲ ਹੋਵੋ

You May Also Like

Detailed Estimates of Buildings: Step-by-Step Guide
Cost & Estimation

Detailed Estimates of Buildings: Step-by-Step Guide

Learn how to prepare detailed estimates—measurement forms, abstract of cost, item-wise rates. Includes single-room and two-room building examples.

ਹੋਰ ਪੜ੍ਹੋ
ਭਾਰਤ ਨਿਰਮਾਣ ਮਜ਼ਦੂਰੀ ਦਰਾਂ 2026: ₹450–₹1,200/ਦਿਨ ਰਾਜ-ਵਾਰ
Cost & Estimation

ਭਾਰਤ ਨਿਰਮਾਣ ਮਜ਼ਦੂਰੀ ਦਰਾਂ 2026: ₹450–₹1,200/ਦਿਨ ਰਾਜ-ਵਾਰ

ਅਣਕੁਸ਼ਲ ₹450–₹650/ਦਿਨ, ਰਾਜ ਮਿਸਤਰੀ ₹600–₹900. ਰਾਜ-ਵਾਰ 2026 ਦਰਾਂ + ਓਵਰਟਾਈਮ ਨਿਯਮ। ਤੁਰੰਤ ਬਜਟ ਲਈ ਮੁਫ਼ਤ Labour Cost Estimator।

ਹੋਰ ਪੜ੍ਹੋ
10×10 ਕਮਰੇ ਲਈ ਈਂਟ, ਸੀਮੈਂਟ ਅਤੇ ਰੇਤ ਦੀ ਮਾਤਰਾ ਦੀ ਗਣਨਾ ਕਿਵੇਂ ਕਰੀਏ
Cost & Estimation

10×10 ਕਮਰੇ ਲਈ ਈਂਟ, ਸੀਮੈਂਟ ਅਤੇ ਰੇਤ ਦੀ ਮਾਤਰਾ ਦੀ ਗਣਨਾ ਕਿਵੇਂ ਕਰੀਏ

ਭਾਰਤ ਵਿੱਚ 10×10 ਕਮਰੇ ਲਈ ਈਂਟਾਂ, ਸੀਮੈਂਟ ਅਤੇ ਰੇਤ ਦੀ ਲੋੜ—ਕਦਮ-ਦਰ-ਕਦਮ ਗਣਨਾ। ਸੂਤਰ, ਹੱਲ ਕੀਤੀ ਉਦਾਹਰਣ ਅਤੇ ਮੁਫਤ ਈਂਟ ਕੈਲਕੁਲੇਟਰ।

ਹੋਰ ਪੜ੍ਹੋ
Approximate Estimates: Plinth Area, Cubical Content & Unit Base Methods
Cost & Estimation

Approximate Estimates: Plinth Area, Cubical Content & Unit Base Methods

Learn three methods for quick project budgets—plinth area, cubical content, and unit base. Worked examples for residential and commercial buildings in India.

ਹੋਰ ਪੜ੍ਹੋ
Earthwork Calculation: Excavation and Filling
Cost & Estimation

Earthwork Calculation: Excavation and Filling

Learn how to calculate earthwork excavation and filling quantities. Trapezoidal and prismoidal formulae for roads, foundations, and trenches.

ਹੋਰ ਪੜ੍ਹੋ
Introduction to Estimating and Costing in Construction
Cost & Estimation

Introduction to Estimating and Costing in Construction

Learn what estimating and costing means in construction, why it matters for contractors, the types of estimates, and what data you need before starting.

ਹੋਰ ਪੜ੍ਹੋ

ਸ਼ੁਰੂਆਤੀ ਪਹੁੰਚ ਲਓ

ਆਪਣੀ ਈਮੇਲ ਅਤੇ ਵਾਟਸਐਪ ਨੰਬਰ ਦਾਖਲ ਕਰੋ। ਅਸੀਂ ਤੁਹਾਨੂੰ ਸ਼ੁਰੂਆਤੀ ਯੂਜ਼ਰ ਵਜੋਂ ਜੋੜਾਂਗੇ ਅਤੇ ਐਪ ਲਿੰਕ ਭੇਜਾਂਗੇ।

Yojo Team Management
Yojo Sites Management