Introduction
A detailed estimate breaks the project into items (earthwork, concrete, brickwork, plastering, etc.), computes quantities for each, and multiplies by workable rates to get total cost.
It is prepared in two stages:
- Details of measurements – Quantities
- Abstract of estimated cost – Amounts
This guide walks through the process with a single-room building example.
Stage 1: Details of Measurements
Division of Work
Divide the work into items such as:
- Earthwork excavation
- CC bed for foundation
- RR masonry / brick masonry
- RCC (lintels, beams, slab)
- Sand filling, flooring
- Plastering, white washing, painting
- Doors, windows, fittings
Measurement Form
For each item, use columns:
| S.No. | Description | No. | Length (m) | Breadth (m) | Depth/Height (m) | Quantity | Notes |
|---|---|---|---|---|---|---|---|
| 1 | Earthwork excavation | 2 | 6.2 | 0.9 | 1.4 | 15.264 | Long walls |
| 2 | 3.4 | 0.9 | 1.4 | 8.568 | Short walls | ||
| Total | 24.192 cum |
Quantity = No. × L × B × H
Use long wall–short wall or centre line methods as appropriate.
Deductions
For brickwork, deduct door and window openings:
- Opening volume = L × Wall thickness × H
- Also deduct lintel volume if included in wall
- Net brickwork = Gross − Deductions
Stage 2: Abstract of Estimated Cost
Abstract Format
| Item No. | Description | Quantity | Unit | Rate (₹) | Amount (₹) |
|---|---|---|---|---|---|
| 1 | Earthwork excavation | 24.192 | cum | 465/10 cum | 1,125.00 |
| 2 | CC (1:4:8) for foundation | 5.184 | cum | 4,545/cum | 23,561.28 |
| ... | Total |
Rates come from rate analysis or standard schedule of rates.
Typical Items for Single-Room Building
- Earthwork excavation
- CC (1:4:8) bed for foundation
- RR masonry in CM (1:6) for footings and basement
- Sand filling in basement
- Brick masonry in CM (1:6) for superstructure (net of openings)
- RCC (1:2:4) for lintels, beams
- RCC (1:2:4) for roof slab
- CC (1:5:10) for flooring
- Flooring (mosaic/tiles)
- Doors, windows (supply and fixing)
- Plastering with CM (1:6)
- White washing / colour washing
- Painting
- Provision for water supply & sanitary @ 12.5%
- Provision for electrification @ 7.5%
- Provision for architectural appearance @ 2%
- Provision for unforeseen items @ 2%
- P.S. & contingencies @ 4%
Example Abstract (Single Room, Load Bearing)
Approximate costs (rates illustrative):
| Item | Qty | Unit | Rate | Amount (₹) |
|---|---|---|---|---|
| Earthwork excavation | 24.192 | cum | 465/10 cum | 1,125 |
| CC (1:4:8) | 5.184 | cum | 4,545/cum | 23,561 |
| RR masonry CM (1:6) | 10.94 | cum | 1,391/cum | 15,218 |
| Sand filling | 8.96 | cum | 195/10 cum | 175 |
| Brick masonry CM (1:6) | 18.03 | cum | 2,291/cum | 41,307 |
| RCC lintels/beams | 1.984 | cum | 6,030/cum | 11,964 |
| RCC slab | 3.09 | cum | 6,030/cum | 18,633 |
| CC flooring | 1.86 | cum | 1,452/cum | 2,701 |
| Doors, windows, plastering, flooring, painting, etc. | ~30,000 | |||
| Subtotal | ~1,64,000 | |||
| Water supply @ 12.5% | 20,500 | |||
| Electrification @ 7.5% | 12,300 | |||
| Architectural @ 2% | 3,280 | |||
| Unforeseen @ 2% | 3,280 | |||
| P.S. & contingencies @ 4% | 6,560 | |||
| Grand Total | ~2,10,000 |
Factors Affecting Detailed Estimate
- Quantity and transport of materials – Bulk purchase and transport reduce cost.
- Site location – Affects transport, damage, and storage.
- Local labour – Skill, availability, and wages vary by region. Use current labour rates for your area.
What the Estimate Should Include
- Report – Brief description and assumptions
- Specifications – General and detailed
- Drawings – Plans, elevations, sections
- Design calculations – Where applicable
- Standard schedule of rates – Reference for rates
Petty Supervision and Contingencies
Usually 4% of the estimate is added for:
- Minor supervision
- Unforeseen items
- Rounding
This is separate from contractor profit, which may be added in tender or negotiated separately.
Data: Fixing Unit Rates
Data = Process of working out cost or rate per unit of each item.
- Material and labour quantities from Standard Data Book (SDB)
- Rates from current standard schedule of rates
- Lead statement for transport and conveyance
Rate per unit includes:
- Materials (first cost, freight, transport)
- Labour (number × wage per day)
- Equipment/T&P (1–2% of estimate)
- Overheads (4% of estimate)
Next Steps
- Rate Analysis – How to derive unit rates from materials and labour
- RCC & Steel Estimation – Reinforcement quantities and bar bending schedule
ଆପଣଙ୍କ ନିର୍ମାଣ ବ୍ୟବସାୟକୁ ପରିବର୍ତ୍ତନ କରିବାକୁ ପ୍ରସ୍ତୁତ କି?
ଆଜି ହିଁ Yojo ସହିତ ଆପଣଙ୍କ ସାଇଟ୍ଗୁଡିକୁ କାର୍ଯ୍ୟକ୍ଷମ ଭାବେ ପରିଚାଳନା ଆରମ୍ଭ କରନ୍ତୁ।
Yojo ମାଗଣାରେ ଟ୍ରାଇ କରନ୍ତୁConstruction Management Expert
Senior Construction Consultant at Yojo
10+ years ଅଭିଜ୍ଞତା
ସମୀକ୍ଷା ତାରିଖ ମାର୍ଚ୍ଚ 10, 2026
Yojo Team ବିଷୟରେ
10+ ବର୍ଷର ଅଭିଜ୍ଞତା ସହିତ ନିର୍ମାଣ ପରିଚାଳନା ବିଶେଷଜ୍ଞ, ଭାରତୀୟ ଠେକେଦାରଙ୍କୁ ଉନ୍ନତ ବ୍ୟବସାୟ ଗଠନରେ ସହାୟତା କରନ୍ତି। ନିର୍ମାଣ ସାଇଟ୍ ପାଇଁ ଡିଜିଟାଲ ରୂପାନ୍ତରରେ ବିଶେଷତା।