Back to Blog
Cost & Estimationअंदाज आणि खर्च

Detailed Estimates of Buildings: Step-by-Step Guide

Learn how to prepare detailed estimates—measurement forms, abstract of cost, item-wise rates. Includes single-room and two-room building examples.

5 min read
By Yojo Team
प्रकाशित: १० मार्च, २०२६
Detailed Estimates of Buildings: Step-by-Step Guide - Yojo construction management blog

Introduction

A detailed estimate breaks the project into items (earthwork, concrete, brickwork, plastering, etc.), computes quantities for each, and multiplies by workable rates to get total cost.

It is prepared in two stages:

  1. Details of measurements – Quantities
  2. Abstract of estimated cost – Amounts

This guide walks through the process with a single-room building example.

Stage 1: Details of Measurements

Division of Work

Divide the work into items such as:

  • Earthwork excavation
  • CC bed for foundation
  • RR masonry / brick masonry
  • RCC (lintels, beams, slab)
  • Sand filling, flooring
  • Plastering, white washing, painting
  • Doors, windows, fittings

Measurement Form

For each item, use columns:

S.No.DescriptionNo.Length (m)Breadth (m)Depth/Height (m)QuantityNotes
1Earthwork excavation26.20.91.415.264Long walls
23.40.91.48.568Short walls
Total24.192 cum

Quantity = No. × L × B × H

Use long wall–short wall or centre line methods as appropriate.

Deductions

For brickwork, deduct door and window openings:

  • Opening volume = L × Wall thickness × H
  • Also deduct lintel volume if included in wall
  • Net brickwork = Gross − Deductions

Stage 2: Abstract of Estimated Cost

Abstract Format

Item No.DescriptionQuantityUnitRate (₹)Amount (₹)
1Earthwork excavation24.192cum465/10 cum1,125.00
2CC (1:4:8) for foundation5.184cum4,545/cum23,561.28
...Total

Rates come from rate analysis or standard schedule of rates.

Typical Items for Single-Room Building

  1. Earthwork excavation
  2. CC (1:4:8) bed for foundation
  3. RR masonry in CM (1:6) for footings and basement
  4. Sand filling in basement
  5. Brick masonry in CM (1:6) for superstructure (net of openings)
  6. RCC (1:2:4) for lintels, beams
  7. RCC (1:2:4) for roof slab
  8. CC (1:5:10) for flooring
  9. Flooring (mosaic/tiles)
  10. Doors, windows (supply and fixing)
  11. Plastering with CM (1:6)
  12. White washing / colour washing
  13. Painting
  14. Provision for water supply & sanitary @ 12.5%
  15. Provision for electrification @ 7.5%
  16. Provision for architectural appearance @ 2%
  17. Provision for unforeseen items @ 2%
  18. P.S. & contingencies @ 4%

Example Abstract (Single Room, Load Bearing)

Approximate costs (rates illustrative):

ItemQtyUnitRateAmount (₹)
Earthwork excavation24.192cum465/10 cum1,125
CC (1:4:8)5.184cum4,545/cum23,561
RR masonry CM (1:6)10.94cum1,391/cum15,218
Sand filling8.96cum195/10 cum175
Brick masonry CM (1:6)18.03cum2,291/cum41,307
RCC lintels/beams1.984cum6,030/cum11,964
RCC slab3.09cum6,030/cum18,633
CC flooring1.86cum1,452/cum2,701
Doors, windows, plastering, flooring, painting, etc.~30,000
Subtotal~1,64,000
Water supply @ 12.5%20,500
Electrification @ 7.5%12,300
Architectural @ 2%3,280
Unforeseen @ 2%3,280
P.S. & contingencies @ 4%6,560
Grand Total~2,10,000

Factors Affecting Detailed Estimate

  1. Quantity and transport of materials – Bulk purchase and transport reduce cost.
  2. Site location – Affects transport, damage, and storage.
  3. Local labour – Skill, availability, and wages vary by region. Use current labour rates for your area.

What the Estimate Should Include

  • Report – Brief description and assumptions
  • Specifications – General and detailed
  • Drawings – Plans, elevations, sections
  • Design calculations – Where applicable
  • Standard schedule of rates – Reference for rates

Petty Supervision and Contingencies

Usually 4% of the estimate is added for:

  • Minor supervision
  • Unforeseen items
  • Rounding

This is separate from contractor profit, which may be added in tender or negotiated separately.

Data: Fixing Unit Rates

Data = Process of working out cost or rate per unit of each item.

  • Material and labour quantities from Standard Data Book (SDB)
  • Rates from current standard schedule of rates
  • Lead statement for transport and conveyance

Rate per unit includes:

  • Materials (first cost, freight, transport)
  • Labour (number × wage per day)
  • Equipment/T&P (1–2% of estimate)
  • Overheads (4% of estimate)

Next Steps

तुमच्या बांधकाम व्यवसायाचे रूपांतर करण्यास तयार आहात?

आजच Yojo सोबत तुमच्या साइट्स प्रभावीपणे व्यवस्थापित करणे सुरू करा.

Yojo मोफत वापरा
Share this article:
समीक्षा करणार

Construction Management Expert

Senior Construction Consultant at Yojo

10+ Years ExperienceCertified Construction Manager

10+ years अनुभव

समीक्षा झाले १० मार्च, २०२६

Y

Yojo Team विषयी

भारतीय ठेकेदारांना चांगले व्यवसाय बनवण्यात मदत करणारा 10+ वर्षांच्या अनुभवाचा बांधकाम व्यवस्थापन तज्ञ. बांधकाम साइट्ससाठी डिजिटल परिवर्तनात विशेषता.

बांधकाम व्यवस्थापन तज्ञ10+ वर्षांचा अनुभव
निपुणता:
बांधकाम व्यवस्थापनमजूर व्यवस्थापनसाइट ऑपरेशन्स

Frequently Asked Questions

वेटलिस्टमध्ये सामील व्हा

आम्ही लॉन्च करताना प्रथम जाणून घ्या.

वेटलिस्टमध्ये सामील व्हा

प्रारंभिक प्रवेश मिळवा

તમારો ઈમેલ અને WhatsApp નંબર દાખલ કરો. અમે તમને શરૂઆતના યુઝર તરીકે ઉમેરીશું અને એપ લિંક મોકલીશું.

Yojo Team Management
Yojo Sites Management