Introduction
Rate analysis (or data) is the process of working out the cost per unit of each item—e.g., ₹/cum for brickwork, ₹/sq m for plastering.
The rate depends on:
- Specifications (quality, proportion, method)
- Material quantities and costs
- Labour types and wages
- Site location and conveyance
- Overheads and profit
This guide explains the process with lead statements and worked examples.
Purpose of Rate Analysis
- Unit cost – Actual cost per unit of work
- Economy – Identify economical materials and methods
- Extra items – Price items not in the contract
- Schedule revision – Update rates when material or labour costs change
Lead Statement
Lead = Distance from source of material to construction site (in km).
Conveyance cost depends on lead and road type:
| Road type | Factor |
|---|---|
| Metalled road (MT) | 1.0 |
| Cart track (CT) | 1.1 |
| Sandy track (ST) | 1.4 |
Equivalent lead = (Lead in MT × 1.0) + (Lead in CT × 1.1) + (Lead in ST × 1.4)
Conveyance charge = Equivalent lead × Rate per km
Example Lead Statement
| Material | Rate at source | Lead (km) | Conveyance | Total at site |
|---|---|---|---|---|
| MT | CT | ST | ||
| 40 mm HBG metal | ₹120/cum | — | 5 | 7 |
| River sand | ₹15/cum | 3 | 2 | 6 |
| Cement | ₹135/bag | 2 | — | 4 |
Material Cost Formulae
Cement (density 1440 kg/cum)
- 1 bag = 50 kg
- Cost per cum cement = (Cost per bag / 50) × 1440
Wet vs Dry Concrete
- 1 cum wet concrete ≈ 1.52 cum dry materials (bulking)
- Weight of concrete ≈ 1440 kg/cum
Cement in Concrete (e.g., 1:2:4)
Cement (bags) = [1 / (1+2+4)] × 1.52 × Volume × (1440/50)
For 20 cum RCC (1:2:4):
- Cement = (1/7) × 1.52 × 20 × 28.8 ≈ 125 bags
- Sand = (2/7) × 1.52 × 20 = 8.69 cum
- Coarse aggregate = (4/7) × 1.52 × 20 = 17.37 cum
Cement in Mortar (e.g., 1:4)
Cement fills voids in sand. For 1 cum CM (1:4):
- Cement = (1/4) × 1 = 0.25 cum = 7.2 bags
- Sand = (4/4) × 1 = 1 cum
Labour Classification
| Type | Typical share | Use |
|---|---|---|
| Skilled I class | 30% | Mason I, Brick layer I |
| Skilled II class | 70% | Mason II, Brick layer II |
| Unskilled | — | Mazdoor (men/women) |
Rates are taken from standard schedule of rates. For current Indian rates, see our labour rates guide.
Worked Example 1: Plastering CM (1:4), 20 mm Thick, 10 sq m
Data (per 10 sq m):
- 0.21 cum CM (1:4)
- 0.66 no. Brick layer I class
- 1.54 no. Brick layer II class
- 0.5 no. Men mazdoor
- 3.2 no. Women mazdoor
- L.S. sundries
Lead statement: Sand ₹112/cum at site, Cement ₹2,100/tonne at site.
Cost of CM (1:4) for 0.21 cum:
- Cement = (1/4) × 0.21 × 1.44 × 2100 = ₹158.76
- Sand = (4/4) × 0.21 × 112 = ₹23.52
- Total = ₹182.28
Labour (illustrative rates): Mason I ₹100/day, Mason II ₹80/day, Mazdoor ₹60/day, Mixing ₹16/cum.
| Item | Qty | Rate | Amount (₹) |
|---|---|---|---|
| CM (1:4) | 0.21 cum | 182.28/0.21 | 182.28 |
| Brick layer I | 0.66 | 100 | 66.00 |
| Brick layer II | 1.54 | 80 | 123.20 |
| Men mazdoor | 0.5 | 60 | 30.00 |
| Women mazdoor | 3.2 | 60 | 192.00 |
| Mixing | 0.21 cum | 16 | 3.36 |
| Sundries | L.S. | 3.36 | |
| Total | ₹625 per 10 sq m |
Rate = ₹62.50 per sq m.
Worked Example 2: RR Masonry in CM (1:6), 1 cum
Data (per 1 cum):
- 1.1 cum rough stone
- 0.34 cum CM (1:6)
- 0.54 no. Mason I
- 1.26 no. Mason II
- 1.4 no. Men mazdoor
- 1.4 no. Women mazdoor
- L.S. sundries
Lead statement: Stone ₹350/cum, Sand ₹112/cum, Cement ₹2,100/tonne at site.
Cost of CM (1:6) for 0.34 cum:
- Cement = (1/6) × 0.34 × 1.44 × 2100 = ₹171.36
- Sand = (6/6) × 0.34 × 112 = ₹38.08
- Total = ₹209.44
| Item | Qty | Rate | Amount (₹) |
|---|---|---|---|
| Rough stone | 1.1 cum | 350 | 385.00 |
| CM (1:6) | 0.34 cum | 209.44 | 209.44 |
| Mason I | 0.54 | 100 | 54.00 |
| Mason II | 1.26 | 80 | 100.80 |
| Men mazdoor | 1.4 | 60 | 84.00 |
| Women mazdoor | 1.4 | 60 | 84.00 |
| Mixing | 0.34 cum | 16 | 5.44 |
| Sundries | L.S. | 18.04 | |
| Total | ₹941 per cum |
Overheads and Profit
Typical additions:
- Tools & plant – 1–2% of estimate
- Overheads – 4% (office, depreciation, staff, etc.)
- Contractor profit – 8–10% (if not already in rate)
These may be built into the unit rate or added at the end of the abstract.
Next Steps
- RCC & Steel Estimation – Reinforcement quantities
- Labour Rates India 2026 – Current wage benchmarks
ನಿಮ್ಮ ನಿರ್ಮಾಣ ವ್ಯವಸಾಯವನ್ನು ಪರಿವರ್ತಿಸಲು ಸಿದ್ಧರಾ?
ಇಂದೇ Yojo ಜೊತೆ ನಿಮ್ಮ ಸೈಟ್ಗಳನ್ನು ಪರಿಣಾಮಕಾರಿಯಾಗಿ ನಿರ್ವಹಿಸಲು ಪ್ರಾರಂಭಿಸಿ.
Yojo ಉಚಿತವಾಗಿ ಪ್ರಯತ್ನಿಸಿConstruction Management Expert
Senior Construction Consultant at Yojo
10+ years ಅನುಭವ
ಸಮೀಕ್ಷಿಸಿದ ದಿನಾಂಕ ಮಾರ್ಚ್ 10, 2026
Yojo Team ಕುರಿತು
10+ ವರ್ಷಗಳ ಅನುಭವದೊಂದಿಗೆ ನಿರ್ಮಾಣ ನಿರ್ವಹಣಾ ತಜ್ಞ, ಭಾರತೀಯ ಠೇಕಾಳಿಗಳಿಗೆ ಉತ್ತಮ ವ್ಯವಸಾಯಗಳನ್ನು ನಿರ್ಮಿಸಲು ಸಹಾಯ ಮಾಡುತ್ತಾರೆ. ನಿರ್ಮಾಣ ಸೈಟ್ಗಳಿಗಾಗಿ ಡಿಜಿಟಲ್ ರೂಪಾಂತರದಲ್ಲಿ ಪರಿಣತಿ.
ಸಂಬಂಧಿತ ಪುಟಗಳು
ಕಾರ್ಮಿಕ ಆಪ್
ಭಾರತದ ಅತ್ಯುತ್ತಮ ಕಾರ್ಮಿಕ ಆಪ್ — ಉಪಸ್ಥಿತಿ, ವೇತನ ಮತ್ತು ಪೇರೊಲ್
ಕಾರ್ಮಿಕ ಉಪಸ್ಥಿತಿ ಆಪ್
ಒಂದು ಟ್ಯಾಪ್ನಲ್ಲಿ ಉಪಸ್ಥಿತಿ, ಅರ್ಧ ದಿನ ಮತ್ತು ಒವರ್ಟೈಮ್ ಗುರುತಿಸಿ
ದೈನಂದಿನ ವೇತನ ಆಪ್
ಉಪಸ್ಥಿತಿಯಿಂದ ದೈನಂದಿನ ವೇತನವನ್ನು ಸ್ವಯಂಚಾಲಿತವಾಗಿ ಲೆಕ್ಕಹಾಕಿ
ಭಾರತದ ಅತ್ಯುತ್ತಮ ಠೇಕುದಾರ ಆಪ್ಗಳು
ಭಾರತದಲ್ಲಿ ಅತ್ಯುತ್ತಮ ಠೇಕುದಾರ ಆಪ್ಗಳನ್ನು ಹೋಲಿಕೆ ಮಾಡಿ
ಸಾಮಗ್ರಿ ಟ್ರ್ಯಾಕಿಂಗ್ ಆಪ್
ಸಾಮಗ್ರಿ, ಬಳಕೆ ಮತ್ತು ಸ್ಟಾಕ್ ಮಟ್ಟಗಳನ್ನು ಟ್ರ್ಯಾಕ್ ಮಾಡಿ
ನಿರ್ಮಾಣ ಸ್ಟಾಕ್ ನಿರ್ವಹಣೆ
ವಸ್ತುಗಳು, ಉಪಕರಣಗಳು ಮತ್ತು ಸೈಟ್ ಆಸ್ತಿಗಳನ್ನು ರಿಯಲ್-ಟೈಮ್ನಲ್ಲಿ ಟ್ರ್ಯಾಕ್ ಮಾಡಿ


