Introduction

Before you can estimate cost, you must know how each item of work is measured. Indian Standard IS 1200 defines units of measurement for civil engineering works. Using the correct unit ensures your quantities match the schedule of rates and billing format.

This guide summarises units for common construction items in India.

Principles of Unit Classification

Units depend on the nature, shape, and size of work:

NatureUnitExamples
Single itemsNumber (No.)Doors, windows, trusses
LinearRunning metre (RM)Cornice, fencing, handrail, bands of specified width
Areal (surface)Square metre (sq m)Plastering, white washing, partitions of specified thickness
VolumeCubic metre (cum)Earthwork, concrete, masonry

Earthwork

ItemUnit of MeasurementUnit of Payment
Earthwork in excavationcumper cum
Earthwork in filling (foundation trenches)cumper cum
Earthwork in filling (plinth)cumper cum

Concrete

ItemUnitPayment
Lime concrete in foundationcumper cum
Cement concrete in lintelscumper cum
RCC in slabcumper cum
CC or RCC chajja, sunshadecumper cum
LC in roof terracing (thickness specified)sq mper sq m
Cement concrete bedcumper cum
RCC sunshade (specified width & height)cum1 rm (running metre)

Damp Proof Course (DPC)

Thickness should be mentioned. Unit: sq m (per sq m).

Brickwork

ItemUnitPayment
Brickwork in foundationcumper cum
Brickwork in plinthcumper cum
Brickwork in superstructurecumper cum
Thin partition wallssq mper cum
Brickwork in archescumper cum
Reinforced brick work (RB)cumper cum

Use our brick calculator for quick brick, cement, and sand quantities.

Stone Work

ItemUnitPayment
Stone masonrycumper cum

Wood Work

ItemUnitPayment
Door/window frames (chowkhats), rafters, beamscumper cum
Shutters of doors and windows (thickness specified)sq mper sq m
Door/window fittings (hinges, bolts, handles)Numberper number

Steel Work

ItemUnitPayment
Steel reinforcement bars in RCC and RB workQuintalper quintal
Bending, binding of steel reinforcementQuintalper quintal
Rivets, bolts, anchor bolts, Lewis boltsQuintalper quintal
Iron hold fastsQuintalper quintal
Iron railing (height and type specified)Quintalper quintal
Iron grillssq mper sq m

Roofing

ItemUnitPayment
RCC and RB slab roof (excluding steel)cumper cum
LC roof over tiles/brick/stone slab (thickness specified)sq mper sq m
Centering and shuttering (formwork)sq mper sq m
AC sheet roofingsq mper sq m

Plastering, Pointing & Finishing

ItemUnitPayment
Plastering – cement or lime mortar (thickness, proportion specified)sq mper sq m
Pointingsq mper sq m
White washing, colour washing, cement wash (coats specified)sq mper sq m
Distempering (coats specified)sq mper sq m
Painting, varnishing (coats specified)sq mper sq m

Flooring

ItemUnitPayment
25 mm cement concrete over 75 mm lime concrete floorsq mper sq m
25 mm or 40 mm CC floorsq mper sq m
Door and window sills (CC or cement mortar plain)sq mper sq m

Other Items

ItemUnitPayment
Rain water pipe / plain pipe1 RMper RM
Steel/wooden trusses1 No.per No.
Glass panels (supply)sq mper sq m
Fixing of glass panels or glazingNo.per No.

Rules for Measurement (IS 1200)

  1. Finished item – Measure finished work. Description must include materials, transport, labour, tools, plant, and overheads.

  2. Booking order – Length, breadth, height/thickness (L × B × H).

  3. Tolerances:

    • Linear: nearest 0.01 m
    • Area: nearest 0.01 sq m
    • Volume: nearest 0.01 cum
  4. Same work, different conditions – Measure separately under separate items.

  5. Bill of quantities – Fully describe materials, proportions, workmanship, and represent work to be executed.

  6. Masonry heights – Describe separately:

    • Foundation to plinth
    • Plinth to first floor
    • First floor to second floor, and so on.

Next Steps

તમારા બાંધકામ બિઝનેસને પરિવર્તિત કરવા તૈયાર છો?

આજે જ Yojo સાથે તમારી સાઇટ્સ અસરકારક રીતે સંચાલન કરવાનું શરૂ કરો.

Yojo મફત ટ્રાય કરો
Share this article:
સમીક્ષા કરનાર

Construction Management Expert

Senior Construction Consultant at Yojo

10+ Years ExperienceCertified Construction Manager

10+ years અનુભવ

સમીક્ષા થયું 10 માર્ચ, 2026

Y

Yojo Team વિશે

ભારતીય કોન્ટ્રેક્ટર્સને વધુ સારું બિઝનેસ બનાવવામાં મદદ કરનાર 10+ વર્ષના અનુભવ સાથે બાંધકામ સંચાલન નિષ્ણાત. બાંધકામ સાઇટ્સ માટે ડિજિટલ પરિવર્તનમાં વિશેષતા.

બાંધકામ સંચાલન નિષ્ણાત10+ વર્ષનો અનુભવ
નિપુણતા:
બાંધકામ સંચાલનમજૂર સંચાલનસાઇટ ઓપરેશન્સ

Frequently Asked Questions

વેઇટલિસ્ટમાં જોડાઓ

અમે લોન્ચ કરીએ ત્યારે પ્રથમ જાણનારા બનો.

વેઇટલિસ્ટમાં જોડાઓ

You May Also Like

Introduction to Estimating and Costing in Construction
Cost & Estimation

Introduction to Estimating and Costing in Construction

Learn what estimating and costing means in construction, why it matters for contractors, the types of estimates, and what data you need before starting.

વધુ વાંચો
Quantity Takeoff Methods: Long Wall, Short Wall & Centre Line
Cost & Estimation

Quantity Takeoff Methods: Long Wall, Short Wall & Centre Line

Learn how to calculate quantities for foundation, brickwork, and concrete using long wall–short wall and centre line methods. Worked examples for single-room buildings.

વધુ વાંચો
10×10 રૂમ માટે ઈંટ, સિમેન્ટ અને રેતીનું જથ્થો કેવી રીતે ગણતરી કરવી
Cost & Estimation

10×10 રૂમ માટે ઈંટ, સિમેન્ટ અને રેતીનું જથ્થો કેવી રીતે ગણતરી કરવી

ભારતમાં 10×10 રૂમ માટે ઈંટો, સિમેન્ટ અને રેતીની જરૂરિયાતની સ્ટેપ-બાય-સ્ટેપ ગણતરી. ફોર્મ્યુલા, હલ કરેલું ઉદાહરણ અને મફત ઈંટ કેલ્ક્યુલેટર.

વધુ વાંચો
Approximate Estimates: Plinth Area, Cubical Content & Unit Base Methods
Cost & Estimation

Approximate Estimates: Plinth Area, Cubical Content & Unit Base Methods

Learn three methods for quick project budgets—plinth area, cubical content, and unit base. Worked examples for residential and commercial buildings in India.

વધુ વાંચો
Detailed Estimates of Buildings: Step-by-Step Guide
Cost & Estimation

Detailed Estimates of Buildings: Step-by-Step Guide

Learn how to prepare detailed estimates—measurement forms, abstract of cost, item-wise rates. Includes single-room and two-room building examples.

વધુ વાંચો
Earthwork Calculation: Excavation and Filling
Cost & Estimation

Earthwork Calculation: Excavation and Filling

Learn how to calculate earthwork excavation and filling quantities. Trapezoidal and prismoidal formulae for roads, foundations, and trenches.

વધુ વાંચો

શરૂઆતી ઍક્સેસ મેળવો

તમારો ઈમેલ અને WhatsApp નંબર દાખલ કરો. અમે તમને શરૂઆતના યુઝર તરીકે ઉમેરીશું અને એપ લિંક મોકલીશું.

Yojo Team Management
Yojo Sites Management