Introduction
Quantity takeoff means measuring volumes and areas from drawings to arrive at material quantities. For buildings, earthwork, foundation concrete, brickwork in plinth and superstructure can be worked out by two main methods:
- Long wall – short wall method
- Centre line method
- Partly centre line and partly long wall–short wall
This guide explains each method with a worked example for a single-room load-bearing structure.
Long Wall – Short Wall Method
Definitions
- Long wall – Wall along the length of the room
- Short wall – Wall perpendicular to the long wall
How to Get Lengths
- Find centre line lengths of each wall.
- Long wall (out to out) = Centre line length + (½ × breadth) at each end
- Short wall (in to in) = Centre line length − (½ × breadth) at each end
As you move from earthwork → foundation → footings → basement → superstructure:
- Long wall length decreases (breadth reduces)
- Short wall length increases
Quantity = Length × Breadth × Height (or depth).
Example: Single Room 5.3 m × 4.3 m (internal)
Assume:
- Foundation width: 0.9 m, depth: 1.4 m (0.3 + 0.5 + 0.6)
- CC bed: 0.9 m × 0.3 m
- RR masonry footings: 0.6 m × 0.5 m
- RR masonry basement: 0.45 m × 0.6 m
- Brickwork superstructure: 0.30 m × 3.0 m
Centre line length = 2 × (5.3 + 4.3) = 19.2 m
Earthwork excavation:
- Long wall L = 5.3 + 0.45 + 0.45 = 6.2 m
- Short wall L = 4.3 − 0.45 − 0.45 = 3.4 m
- Q = 2 × 6.2 × 0.9 × 1.4 + 2 × 3.4 × 0.9 × 1.4 = 24.192 cum
CC (1:4:8) bed:
- Q = 2 × 6.2 × 0.9 × 0.3 + 2 × 3.4 × 0.9 × 0.3 = 5.184 cum
RR masonry footings:
- Long wall L = 5.3 + 0.3 + 0.3 = 5.9 m
- Short wall L = 4.3 − 0.3 − 0.3 = 3.7 m
- Q = 2 × 5.9 × 0.6 × 0.5 + 2 × 3.7 × 0.6 × 0.5 = 5.76 cum
RR masonry basement:
- Long wall L = 5.3 + 0.225 + 0.225 = 5.75 m
- Short wall L = 4.3 − 0.225 − 0.225 = 3.85 m
- Q = 2 × 5.75 × 0.45 × 0.6 + 2 × 3.85 × 0.45 × 0.6 = 5.184 cum
Brickwork superstructure:
- Long wall L = 5.3 + 0.15 + 0.15 = 5.6 m
- Short wall L = 4.3 − 0.15 − 0.15 = 4.0 m
- Q = 2 × 5.6 × 0.30 × 3.0 + 2 × 4.0 × 0.30 × 3.0 = 17.28 cum (before door/window deductions)
Centre Line Method
When to Use
Suitable when walls have similar cross-section. Total centre line length × breadth × depth gives quantity in one step.
Junction Adjustment
Where cross walls or partitions join the main wall, reduce centre line by half the breadth for each junction.
Total centre line = sum of all walls − (½ × breadth) × number of junctions
Same Example by Centre Line
Centre line length = 2(5.3 + 4.3) = 19.2 m (no internal walls)
Earthwork excavation:
- Q = 19.2 × 0.9 × 1.4 = 24.192 cum
CC bed:
- Q = 19.2 × 0.9 × 0.3 = 5.184 cum
RR masonry footings:
- Q = 19.2 × 0.6 × 0.5 = 5.76 cum
RR masonry basement:
- Q = 19.2 × 0.45 × 0.6 = 5.184 cum
Brickwork superstructure:
- Q = 19.2 × 0.30 × 3.0 = 17.28 cum
Same answers as long wall–short wall, with less calculation.
Partly Centre Line and Partly Long Wall–Short Wall
Use when:
- External walls – Same thickness all around → centre line method
- Internal walls – Different thickness or levels → long wall–short wall method
This is common in practice for buildings with different foundation levels or wall thicknesses.
Choosing a Method
| Situation | Preferred method |
|---|---|
| Simple rectangular room, same section | Centre line |
| Multiple rooms, different wall thicknesses | Long wall–short wall or partly centre line |
| Symmetrical layout | Centre line |
| External + internal with different sections | Partly centre line |
Deductions for Openings
For brickwork in superstructure, deduct door and window openings:
Deduction = Opening length × Wall thickness × Opening height
Deduct lintel volume separately if required. Net brickwork = Gross − Deductions.
Next Steps
- Detailed Estimates of Buildings – Full measurement and abstract for single/double room buildings
- Brick, Cement, Sand for 10×10 Room – Practical material calculation
আপনার নির্মাণ ব্যবসাকে রূপান্তর করতে প্রস্তুত?
আজই Yojo দিয়ে আপনার সাইটগুলি দক্ষভাবে পরিচালনা শুরু করুন।
Yojo বিনামূল্যে ট্রাই করুনConstruction Management Expert
Senior Construction Consultant at Yojo
10+ years অভিজ্ঞতা
পর্যালোচনা তারিখ ১০ মার্চ, ২০২৬
Yojo Team সম্পর্কে
১০+ বছরের অভিজ্ঞতা সহ নির্মাণ ব্যবস্থাপনা বিশেষজ্ঞ যিনি ভারতীয় ঠিকাদারদের উন্নত ব্যবসা গড়তে সাহায্য করেন। নির্মাণ সাইটগুলির জন্য ডিজিটাল রূপান্তরে বিশেষজ্ঞ।


